Public Agenda NewsPaperPublic Agenda NewsPaper
  • General News
  • Politics
  • Business
  • Health
  • Development Agenda
  • World News
  • Features & Opinions
  • Election watch
  • Editorial
Font ResizerAa
Public Agenda NewsPaperPublic Agenda NewsPaper
Font ResizerAa
  • General News
  • Politics
  • Business
  • Health
  • Development Agenda
  • World News
  • Features & Opinions
  • Election watch
  • Editorial
Search
  • General News
  • Politics
  • Business
  • Health
  • Development Agenda
  • World News
  • Features & Opinions
  • Election watch
  • Editorial
Follow US
Breaking NewsGeneral News

Ghana Gas connects pipeline to Aboadze power enclave

Latifa Carlos
Last updated: April 10, 2019 2:57 pm
Latifa Carlos
Share
4 Min Read
SHARE

The Ghana National Gas Company (Ghana Gas) has successfully completed the tie-in of its 11-km gas pipeline from Atuabo to the West African Gas Pipeline at the Aboadze power enclave in the Shama District in the Western Region.

The project, which was completed ahead of schedule and within cost, is expected to pave the way for more reliable energy supply to power plants in Tema and Aboadze, as well as serve non-power gas users.

Following the completion of the tie-in, Ghana Gas is now producing 110 million standard cubic feet (mscf) a day, which can generate about 600 megawatts (MW) of power for the country.

More Read

Ghana can unlock major domestic resources through Structured Philanthropy
Global funding cuts devastating HIV prevention programmes says UNAIDS
Majority: 10% Lithium royalty deal violated mining law
Supreme Court directs Wesley Girls SHS to respond to Muslim Rights allegations
Mahama extends IGP Yohuno’s tenure by two years

The visit

A team of officials from Ghana Gas and journalists went on a tour of the Aboadze power plant at Aboadze yesterday.

During the tour, the Communications Officer of Ghana Gas, Mr Ernest Owusu-Bempah, confirmed that the tie-in had been completed ahead of schedule and that what was left were some civil works that would be completed soon.

“The major work involving the tie-in and push gas to the Volta River Authority has been done. At the moment we are doing about 110mscf a day, which can generate about 600MW of power. What is left are some civil works that will be done soon,” he said.

 Power outage

The completion of the tie-in is expected to help reduce or eliminate the sporadic power outages the country is currently experiencing as a result of the shutdown and other technical challenges.

After the tie-in, the facility now has an integrated port system, which positions it to serve any plant — both power and non-power customers — in the enclave without shutting down to carry out a future hook-up to the metering station.

 Stranded gas

Mr Owusu-Bempah said with the completion of the tie-in, stranded gas would now flow to the plants in Tema for power generation.

Stranded gas is essentially gas that is wasted or unused. Meanwhile, Ghana has had to pay for gas produced by Eni-Ghana, whether it uses the gas or not. That arrangement is part of the contract between Ghana and Eni-Ghana for the Sankofa gas production

Currently, through the Takoradi metering and regulation station, 110mscf of gas is delivered to the VRA thermal plants at Aboadze daily.

Daily Graphic checks indicate that out of the 110mscf, VRA is only consuming about 100mscf because some of its generating units are being maintained.

 Demand of gas

The facility, henceforth, is best placed to distribute about 225mscf through the lines to the Tema enclave through the reverse line connection, while a total volume of 150mscf goes to VRA facilities.

From the same metering station, engineers explained, a total volume of 90mscf would be delivered to the Karpowership after its relocation to Sekondi in June. Amandi Energy would also be supplied with 90mscf.

The manufacturing sector, a ceramic factory in the enclave, is using about 10mscf to power its operations.

 

Source: Graphic.com.gh

Share This Article
Facebook Whatsapp Whatsapp Email Copy Link Print

Latest News

Forestry Commission Debunks Interdiction Claims, Clarifies GHS623,000 Revenue Issue
November 20, 2025
PIAC elects Richard Ellimah as new chair
November 18, 2025
Nsawam City Sporting Club Secures International Transfers for Five Players
November 18, 2025
Ato Forson seeking prudence with 2026 Budget – Prof. Khalid
November 18, 2025
Youth Groups advocate for Economic Inclusion, Job Creation and more
November 15, 2025
STAR-Ghana Foundation launches Five-Year Strategy to boost Youth -Led Development
November 15, 2025
198km Accra–Kumasi Expressway to be completed in three years — Ato Forson
November 14, 2025

You Might Also Like

Breaking NewsHealthtop stories

No Money in Ghana’s Mental Health Fund

November 14, 2025
Breaking NewsGeneral Newstop stories

Sudden altitude change caused August 6 helicopter crash – Report

November 11, 2025
Breaking NewsDevelopment Agendatop stories

Inequality, corruption, threaten Ghana’s moral fabric – Catholic Bishops

November 11, 2025
Breaking NewsBusinesstop stories

Fiscal Reforms Needed to Maximise Gains from Extractive Sector, Says IEA

November 5, 2025

About Us

Public Agenda is fou­nded and owned by Pu­blic Agenda Communic­ations.

Public Agenda was founded as a public interest Me­dia entity. Its Visi­on is to contribute to building a well-i­nformed society where accurate informati­on dissemination is the cornerstone of a democratic, just and equitable society.

Its mission is to inform, guide and bui­ld responsible citiz­enship and accountab­le decision making and strive for excell­ence in the media in­dustry. Public Agenda Communications is managed by a Board of Directors.

Welcome Back!

Sign in to your account

Username or Email Address
Password

Lost your password?